We propose to approve Sabey Data Center’s Building E air quality notice of construction (NOC) application.
Sabey Data Center submitted a notice of construction application for their data center located at 4405 Grant Road, in East Wenatchee. Sabey is proposing to expand its existing Intergate Columbia II data center by installing 14 2.25–2.5 MWe emergency diesel generators and one 1–1.5 MWe emergency diesel generator in Building E.
Emission increases from this project include:
- 35 tons per year nitrogen oxides (NOx)
- 6.96 tons per year carbon monoxide (CO)
- 2.1 tons per year particulate matter (PM)
- 2.1 tons per year particulate matter (PM10)
- 2.1 tons per year particulate matter (PM2.5)
- 1.5 tons per year volatile organic compounds (VOCs)
- 0.64 tons per year diesel engine exhaust, particulates (DEEP)
- 0.02 tons per year sulfur dioxide (SO2)
Documents for review
- Sabey notice of construction (NOC) application and supporting documents
- Sabey draft permit
- Sabey technical support document
- Sabey Tier 2 recommendation letter and health impact assessment (HIA)
- Sabey SEPA determination of nonsignificance (DNS) and environmental checklist
We determined this proposal satisfies the requirements of Chapter 173-400 WAC. We plan to approve the application.
Tentative public hearing
(if requested by July 30, 2026, 11:59 p.m.)
Tuesday, August 18, 2026, 6 p.m. online
We will hold a public hearing if there is significant public interest. If we do not receive significant written requests for a public hearing by July 30, 2026, then the online public hearing will be cancelled. We will update this web page either cancelling the public hearing or adding a link to the public hearing. If you request a public hearing, please tell us if you need interpretation in a language other than English.
To comment by August 24, 2026, use one of the ways listed below.
To find out if there are more records for this project, contact our Public Records Office.
This notice was posted on July 15, 2026.
Background
Data centers, sometimes called server farms, house the servers that manage email, store data, and run apps (computer or mobile). If you shop on the web or use social media, store photos in "the cloud," or use AI (artificial intelligence), you're using a data center. Most of the data centers regulated by Ecology are located in Quincy and the Wenatchee area because those areas have dependable, lower cost electricity. Sign up for email updates about data centers.
A notice of construction permit is required before installing a new source of air pollution or modifying an existing source of air pollution. This permit is sometimes called a "pre-construction permit" because a business must have one before starting construction or operating their business.
A notice of construction air permit limits the amount of air pollutants a business can emit.
Comment online
- Use our online comment form
Comment by mail
Washington Department of Ecology Central Regional Office
1250 West Alder Street
Union Gap, WA 98903-0009
Questions
To request ADA accommodation, contact Ecology's ADA Coordinator by email at ecyadacoordinator@ecy.wa.gov, or call 360-407-6831, 711 (relay service), or 877-833-6341 (TTY). More about our accessibility services.