Event detail icon
Comment Period

Glacier Northwest, Inc., Seattle

Comment on a site study

June 1, 2026, 12 a.m. - June 30, 2026, 11:59 p.m. PT

Cleanup work is moving forward at the Glacier Northwest, Inc. cleanup site along the banks of the Lower Duwamish Waterway along W Marginal Way SW and north of the Port of Seattle’s Terminal 115.

We, along with the potentially liable party for the cleanup, Glacier Northwest, Inc., have prepared a remedial investigation report. This report is the result of environmental studies to find out what contamination is present at the site and where it has spread to. 

Between 1913 and 1922, the upland portion of the site was filled with material from the initial dredging and straightening of the Lower Duwamish Waterway. From the 1930s until today, a variety of industrial operations occured on the site ranging from wood treatment to cement distribution. The remedial investigation found contamination in the soil, groundwater, and sediments next to the site.

Learn more by visiting the site webpage, reaching out to Site Manager Cliff Nale, or joining us at our monthly community office hours to talk with us in-person.

Comment online icon

Comment online

Comment by mail icon

Comment by mail

Cliff Nale
PO Box 330316
Shoreline, WA 98133-9716
Questions icon

Questions

Meredith Waldref
Senior Outreach Planner
meredith.waldref@ecy.wa.gov
425-229-3683

To request ADA accommodation, contact Ecology's ADA Coordinator by email at ecyadacoordinator@ecy.wa.gov, or call 360-407-6831, 711 (relay service), or 877-833-6341 (TTY). More about our accessibility services.