Cleanup work concludes at Plutonium Finishing Plant

(Information on this site is considered to be accurate at the time of posting, but is subject to change as new information becomes available.)

Work at the Hanford Site's Plutonium Finishing Plant (PFP), one of the site's most highly contaminated buildings, concluded in November 2021.

Workers cleaning up PFP previously completed demolition of the plant's main processing facility in early 2020. That work was finished using more rigorous safety protocols, thanks in part to intervention by our office and the U.S. Environmental Protection Agency.

However, work paused at the PFP site in March 2020 due to the COVID-19 pandemic. In April 2021, cleanup resumed to loadout debris from the final PFP building – the 236-Z Plutonium Reclamation Facility (PRF).

Completion of work at PFP included a characterization of the remaining slab, application of the clean soil cap, and turnover to surveillance and maintenance. Work on the waste sites in the PFP area is expected to continue in the near future. 

Read more about PFP's demolition history below.

Summary information

Date of incident:  December 14, 2017
Location:

Hanford site, Southeastern Washington

Type of incident: Airborne spread of radioactive contamination
Cause of incident: Demolition activities at Hanford's plutonium finishing plant
Responsible party: U.S. Department of Energy Richland Operations Office
GIF file of PFP before demolition and as of January 2020. Before: massive concrete complex with dozens of buildings. After: mostly dirt and equipment

Hanford's Plutonium Finishing Plant before demolition and during demolition in January 2020 (GIF Courtesy: U.S. Department of Energy)

Status updates

Contamination shut down demolition

In mid-December 2017, Energy and contractor CH2M Hill Plateau Remediation Company (CHPRC) shut down demolition as high winds caused widespread distribution of airborne contaminants, including plutonium and americium. In early 2018, we joined with the EPA to issue an order preventing further demolition work while stronger safety protocols could be designed and put into practice at the site.
 
In the interim, Energy and its contractor tested new safety practices while proceeding with lower-risk work. In summer 2019, together with the EPA, we lifted that order, satisfied that new safety protocols would protect worker and public health and safety. That action cleared the way for full demolition to resume.

PFP work completed November 2021

On April 6, workers conducted a full-scale dry-run of the demolition work package to gauge workforce readiness to resume demolition work.

Following a successful walkthrough, demolition work commenced on April 6 with items located on the 234-5Z pad. This phase of demolition concluded in spring 2021.

In summer 2021, Energy finished demolition of the final PFP building — PRF — which was reduced to its foundation slab of concrete, and the associated rubble safely disposed of in Hanford’s massive landfill after that.
 
The process to demolish and dispose of the Plutonium Finishing Plant complex — which at its peak numbered some 60 buildings — began more than 20 years ago. Open-air demolition on the plant began in late 2016 using heavy equipment to tear down its walls.

PFP demolition background

Plutonium and americium contamination was detected at PFP in summer 2017. Work resumed when it appeared that no additional contamination was coming from the facilities. However, when an ancillary building known as the reclamation facility was knocked down to its foundation in December of that year, there was a widespread release of plutonium and americium.
 
We were extremely concerned about those releases. Not only did the contamination spread far beyond the work containment zone established by Energy, contamination was carried off-site in workers’ vehicles. We were not convinced that Energy had adequate safeguards or monitoring in place to ensure safe operations. After major releases of contamination earlier in 2017, work was allowed to continue. The result was an even more widespread release. That clearly is unacceptable for worker and public health and safety, and threatened other Hanford cleanup operations.
 
After we joined with EPA to prohibit further demolition, we worked with Energy to ensure that it drew up and would be able to adhere to adequate protections such as the establishment of containment zones within which heightened safety measures are deployed, and the calibration and placement of monitors intended to signal contamination releases above acceptable regulatory limits.

Work resumed in phases

As new safety protocols were introduced, we allowed work on lower-risk tasks to resume. As the new safety approaches proved to be effective, we allowed gradually more risky work, eventually leading back to full demolition. Demolition concluded in November 2021.

Surveillance and maintenance

PFP will be placed in a surveillance and maintenance mode until waste sites cleanup, which comprises largely of contaminated soil in the area. These monitoring activities help maintain safe and stable conditions until that time. 

A highly contaminated facility

PFP was a complex of more than 60 buildings on the Hanford site. Irradiated fuel rods from Hanford’s nine nuclear reactors were processed elsewhere on site to extract plutonium in liquid form – plutonium nitrate. At PFP, that liquid was processed into hockey puck-sized “buttons” that were then sent to nuclear weapons production facilities elsewhere in the country. That work left PFP’s two central processing facilities among the most contaminated buildings at Hanford.

Plutonium Finishing Plant Timeline

2016

Open air demolition begins late 2016.

2017

June 8 — Plutonium americium contamination first detected; 31 workers test positive for internal radiation.

Dec. 14 — We're notified by Energy that work stopped after workers' air samplers show elevated radiation levels. Elevated readings occurred Dec. 8, Dec. 9 and Dec. 12. Work resumes later on Dec. 14 after no further contamination is detected.

Dec. 15 — Contamination found at air monitor outside established control area. Subsequent monitoring finds contamination on hood of vehicle, a concrete barrier, mobile office trailers and on a dumpster. Work continues.

Dec. 16 — Workers cover demolition debris with dirt and with glue-like fixative. New surveys find contamination on cars and around office trailers. A number of employees drive home, potentially tracking radioactive contamination off site and potentially into homes. Demolition continues.
Dec. 17 — Work stopped when contractor, CHPRC, is notified of the earlier contamination found. Workers apply more fixatives to try to prevent more contamination spread.

2018

Jan. 9 — We issue letter, with EPA, prohibiting further demolition work until we’re certain work can continue safely without threat to workers, the public or the environment. The stop-work order is based on Article 32 of Tri-Party Agreement, a legal agreement signed by our agency, Energy and EPA. Article 32 gives any of the agencies authority to stop work if the work endangers health and safety of workers or public. Energy says seven worker vehicles and 16 government or contractor vehicles were contaminated with plutonium, and at least 269 Hanford workers requested blood tests, or bioassays.

Jan. 30 — State Health Department issues a letter formally expressing concerns. Health’s findings show contamination in air samples taken around Hanford site. Letter includes bulleted list of requests, many of which we had previously requested from Energy.

February — Contamination detected by state air monitors as far as 10 miles from the PFP demolition site. We continue to receive reports and news from other sources saying contamination has been found in air filters in worker’s cars, both inside and outside expanding PFP demolition zone. Some toxic airborne contaminants from the buildings have been ingested by workers.

March 22 — After December spread of contamination, 281 Hanford workers tested for radiation doses. Tests show 42 inhaled or ingested contamination. State experts consider the amounts found too small to pose health risk. 

June — With EPA, we approve resumption of lower-risk demolition activities.

2019

March — After reviewing, with EPA, Energy’s workscope plans and safety procedure improvements, as well as monitoring progress for ongoing lower-risk activities, we allow additional lower-risk demolition to proceed.

June — With EPA, we lift stop-work order, allowing final phase of higher-risk work to proceed.

Oct. 30 — Work of lower-risk demolition concludes.

Nov. 7 — Higher-risk final phase of demolition resumes.

2020

January  Demolition of PFP's main processing facility finishes. 

Feb. 10 — Cleanup work of PFP's 236-Z Plutonium Reclamation Facility resumes.

March April 2021 — PFP project gets put into shutdown mode due to COVID-19 pandemic.

2021

April 6 — Work resumes at PFP.

November – Demolition work concludes for PFP. 

2022

Energy anticipates preparation for waste sites remediation. 

sunrise overlooks a dark site covered in concrete.

The Plutonium Finishing Plant contamination control cap. (Photo Courtesy: U.S. Department of Energy)

News releases

None at this time
 

Media contact

Ryan Miller, Communications Manager, Ryan.Miller@ecy.wa.gov, 509-537-2228 ,ecyHanford