Project sponsor
WSDOT Environmental Services Office
310 Maple Park Avenue SE
PO Box 47331
Olympia, WA 98504
Evan Dulan
DulinEv@wsdot.wa.gov
360-704-6328
Project details
Project status
- Long-term management phase begins: January 2011
- Final credit release: July 16, 2007
- Initial credit release: June 16, 2003
- Mitigation Banking Instrument (MBI) certification date: June 13, 2003
- MBI Amendment 1: March 3, 2005
- MBI Amendment 2: February 22, 2007
Site location
- Water Resource Inventory Area 41, Moses Lake, Grant County
- The project is adjacent to the Pelican Horn arm of Moses Lake
- Site location map