Cleaning up: Fieldwork on Bellingham's busy working waterfront

How do you investigate contamination in a busy mixed-use marine trades area on a former landfill — and still keep the waterfront working? Very carefully, with high-tech tools and lots of communication!

Crews with gas analyzers, drilling machines, and excavation equipment are getting set to do just that. They’re carefully coordinating their investigation work with the Port of Bellingham, waterfront businesses, and us.

Over the past seven years, we’ve overseen the cleanup of portions of the Central Waterfront site on Bellingham Bay. The port and the City of Bellingham are getting ready to advance the site to its final cleanup step. First, we need additional information to help design the remaining cleanup work.

Contractors will test the soil, groundwater, and air on this busy working waterfront site.

It’s been a busy year for this type of fieldwork on Bellingham Bay. See our other stories about the neighboring cleanup sites: I & J Waterway and Whatcom Waterway

Where is this site in the cleanup process?  And, what happens next?

Graphic links to a webpage explaining the cleanup process.
Previous cleanup work from 2013–2017, called an Interim Action, addressed contamination on portions of the Central Waterfront site. We are now nearing the final steps of Washington’s formal cleanup process, guided by the Model Toxics Control Act (MTCA).

The planned fieldwork, called a pre-remedial design investigation, will provide additional information to complete engineering design of the final cleanup action.

The port and city are conducting this fieldwork in accordance with an Agreed Order with Ecology.

Engineering design and permitting for cleanup will take about two years to complete, with construction work expected as early as 2022.  The cleanup work will include a combination of removing and capping contaminated soil, monitoring conditions, and restricting certain land use activities.

What happened here?

The waterfront area was used for marinas, boat repair, fuel storage, mills, and other business.

Central Waterfront site historical operations.

Beginning in the early 1900s, the site and surrounding tidelands were filled for various industrial uses. Before modern landfill regulations, municipal waste was used to fill in the tidelands to create much of the site’s 51 acre upland area.

What will I see happening on the Bellingham waterfront?

The port and city are cleaning up contamination from this landfill and the site’s other historical industrial uses. Click on the image to the right to view a map of the site’s historical operations.

Investigating soil and groundwater

A direct-push drill rig is heavy equipment, about tractor size.

Direct-push drill rig example.

To prepare for excavation of an isolated petroleum-contaminated area, crews will investigate soil and groundwater on the southern portion of the site. A direct-push drill rig will pull up soil samples from up to 20 feet below the surface at 10 new boring locations. Groundwater samples will be collected through 10 wells total, including 6 new wells. These same 10 wells will be used to learn about the extent of tidal influences on groundwater.

In addition, to understand the quality of groundwater at the northwest corner of the site, crews will install and sample one groundwater monitoring well.

Evaluating existing caps

A key aspect to the final cleanup of this site is to cap contaminated soil and refuse, to prevent them from coming in contact with people and the environment. Crews will visually inspect existing paved areas and note conditions. They also will excavate a series of test pits to determine the thickness of existing gravel that covers sections of the old fill.

Assessing existing natural processes affecting groundwater

Monitored Natural Attenuation (MNA) is how scientists keep watch on the natural processes that reduce levels of contamination in groundwater. Crews will use a network of existing and new MNA wells to sample groundwater, both now and at regular intervals over the long term. 

The pre-remedial design investigation plan has details on the specific locations of these wells.

Investigating landfill gas

A hand-held electronic tool with a digital read-out.

Portable flame ionization detector.

We’ve learned how old landfills age, and can use computer models (like the EPA’s LandGEM model) to estimate landfill gas production and design collection and mitigation systems. Crews will conduct indoor air monitoring using a flame ionization detector to evaluate vapor migration into existing buildings. The flame ionization detector is an instrument that uses a hydrogen flame to burn gases and measure the ions produced.

Crews will also use hand-held analyzers to evaluate soil vapor and take samples from 14 temporary gas probe locations as well as the five existing groundwater monitoring well locations. Crews will also establish seven permanent landfill gas monitoring probe locations.

Assessing groundwater flow

Aerial photo of central waterfront and treatment lagoon.

Looking south over the Central Waterfront site to the neighboring ASB treatment lagoon. May 2019.

A clay berm separates the site from the adjacent industrial waste treatment lagoon located just offshore in the bay, also called the Aerated Stabilization Basin, or ASB. Crews will install four new groundwater wells along the berm to evaluate the effect of the ASB on groundwater flow. (The ASB itself is within the neighboring Whatcom Waterway cleanup site.)

Evaluate the shoreline

In the site’s northwestern corner crews will evaluate the shoreline conditions to determine the need for capping. They will take pictures of the site at different tides, note any damage or deterioration, and compare current and historical conditions.

Funding

Pre-remedial design investigation activities are expected to cost $300,000. The port and city are eligible for reimbursement of up to half of their cost from us through the state’s Remedial Action Grant Program, which helps pay for the cleanup of publicly-owned sites. The Legislature funds the grant program with revenues from a tax on hazardous substances

Cleaning up Bellingham Bay

The Central Waterfront site is one of 12 Bellingham Bay cleanup sites coordinated through the Bellingham Bay Demonstration Pilot.  The pilot is a bay-wide multi-agency effort to clean up contaminated sediment, control sources of sediment contamination, and restore habitat, with consideration for land and water uses. In 2000, participants in this initiative developed the Bellingham Bay Comprehensive Strategy.