Cleanup status
Cleaning up contaminated sites is a key part of our source control efforts. Source control means finding the sources and extent of contamination, then stopping or reducing them before they reach the Lower Duwamish Waterway (LDW).
We manage cleanup of many contaminated sites within the LDW drainage area and are working to add more sites to the list.
- Our Hazardous Waste and Toxics Reduction program manages cleanup sites that are current or former dangerous waste facilities.
- Our Toxic Cleanup program manages multiple sites through the state-supervised formal cleanup process.
- Our Voluntary Cleanup Program assists many other sites.
TCP cleanup sites
Site |
Agreed Orders |
Remedial Investigation |
Feasibility Study |
Cleanup Action Plan |
Cleanup |
Interim Action |
---|---|---|---|---|---|---|
8801 East Marginal Way South | 2006, 2008 | 2011 | In progress | In development | ||
Boeing Field Chevron | 2015 | In progress | In progress | |||
Boeing Isaacson Thompson | 2010 | 2014 | In progress | |||
Crowley (8th Avenue) | 2009 | 2019 | In progress | |||
Douglas Management | 2011 | 2019 | In progress | |||
Duwamish Marine Center | 2011 | 2020 | In progress | |||
Duwamish Shipyard | 2010 | May 2019 | In progress | |||
Emerald Gateway | 2020 | In progress | ||||
Fox Avenue Building | 1991, 2009, 2012, amended 2013 | 2011 | 2012 | 2012, amended 2013 | In progress | 2009 |
Glacier Northwest | 2009 | In progress | ||||
Industrial Container | 2011 | 2020 | In progress | |||
Jorgensen Forge | 2007, Enforcement Order 2015 replaced by Agreed Order in 2017 | In progress | 2014 | |||
North Boeing Field/ Georgetown Steam Plant | 2008 | In progress | 2011 | |||
North Terminal 115 | 2011 | In progress | ||||
Precision Engineering Inc. | 2020 | |||||
Snopac Property | 2019 | In progress | In progress | In development | 2019 & 2021 | |
South Park Landfill | 2009 | 2017 | 2017 | 2017 | 2014, 2016 | |
South Park Marina | 2019 | |||||
Terminal 115 Plant 1 | 2020 | |||||
Whitehead Tyee | 2016 | Work plan in development | 2017 |
HWTR cleanup sites
Site Name |
Agreed Orders |
Remedial Investigation |
Feasibility Study |
Cleanup Action Plan |
Cleanup |
Interim Action |
2010, amended 2015 |
2005 (under dangerous waste permit) |
2007 (under dangerous waste permit) |
2010, amended 2015 |
In progress |
||
Burlington Environmental LLC Georgetown (west of 4th)
|
2014 |
In progress |
In progress |
|||
2002, 2007, 2008 |
2008 |
2009 |
Consent Decree 2014 |
In progress |
Related links
Contact information
LDW Email
LDW@ecy.wa.gov
Brett Carp
Aquatics Unit Supervisor
Brett.Carp@ecy.wa.gov
206-496-7007
Ryan Gardiner
Source Control Project Manager
Ryan.Gardiner@ecy.wa.gov
425-681-5543
Kim Wooten, Ph.D.
Toxics Cleanup Program Regional Section Manager
Kim.Wooten@ecy.wa.gov
425-324-1658